  • 手术室净化装修的工程图纸要求
    来源:http://www.sdyhrs.com 浏览: 发布日期:2017-06-19
    一、施工前确认工程设计图纸和技术要求,并与各进行交流,讨论交叉作业时应该注意的问题。
    First, confirm the engineering design drawings and technical requirements before construction, and communicate with each other, and discuss the problems that should be paid attention to during the cross operation.
    工程施工中,由于未及时与电气沟通,导致插座开关与观察窗重叠。
    In engineering construction, the socket switch and observation window overlap because of not communicating with the electrical professional in time.
    二、检查工程所用主要材料、设备是否合格,必要时要请业主参与检查。
    Two, check whether the main materials and equipment used in the project are qualified. If necessary, please ask the owners to participate in the inspection.
    由于未对观察窗作检查工作,就安装观察窗,业主查看之后对观察窗质量不满意,导致观察窗更换并重新安装。
    As the inspection window is not checked, the observation window is installed. The owner is not satisfied with the quality of the observation window after the view is checked, which results in the replacement of the observation window and re installation.
    三、施工过程中加强进度控制及质量控制。
    Three 、 strengthen the progress control and quality control during the construction.
    四、洁净室施工管理制度要严格执行。
    Four, clean room construction management system should be strictly enforced.
    五、世纪星工程施工中,材料是先到顶板,后到墙板。但是,施工起头基本都是从立墙板开始,然后跟着吊顶板。所以,导致了施工材料需求和材料供给之间的矛盾。
    Five, Century Star project construction, the material is first to the roof, and then to the wallboard. However, the construction starts with the beginning of the vertical wall board, then follows the ceiling board. Therefore, it leads to the contradiction between construction material demand and material supply.
    六、二、三楼有许多板材都是立到楼板大梁底部,由于搬运及吊顶上部布满管线管道,所以板材都切割使用。可以订吊顶高度的板材,然后各房间之间可以用铁皮封堵。
    Six, two, the third floor, many plates are standing to the bottom of the floor beam, because the top of the transport and ceiling covered with pipelines, so cutting plates are used. You can order the ceiling height of the sheet, and then between the rooms can be blocked with iron.
    七、门洞预留的时候未考虑直流平水泥及PVC地板的厚度,导致洁净室钢质门安装后门底部与地坪摩擦。
    When the reservation is not considered seven, DC leveling cement and PVC the thickness of the floor, resulting in clean room to install the back door at the bottom of the steel door and floor friction.
    八、风淋室安装以后风淋的风速较小,不能满足吹淋的要求。检查多次后,是电机的相序接错,导致风机反转,风速过小。
    Eight 、 after the installation of the wind shower room, the wind speed of the wind shower is small, and it can not meet the requirements of blowing. After checking several times, it is the phase sequence of the motor, which causes the fan to reverse and the wind speed is too small.
    九、一楼板材先到货的为一些根据图纸尺寸的非标板和标准板,剩余的很大一部分是要施工过程中测量尺寸加工的。由于非标板材尺寸与现场的差异及没有非标板材的衔接,导致板缝对齐重新调整及板材排布过程中缺少材料,终导致施工进展不明显。
    Nine, the first floor of the plate first arrival for some drawings according to the size of the non-standard plate and standard plate, the remaining large part of the construction process is to measure the size of the processing. Because of the difference in size of sheets and the scene and no convergence of non-standard sheet, leading to a lack of material re adjustment and arrangement of plate slab alignment, eventually leading to the construction progress is not obvious.