  • 如何做好洁净厂房建设/改造的报价?|净之源净化
    来源:http://www.sdyhrs.com 浏览: 发布日期:2017-10-18
    如何做好洁净厂房建设/改造的报价?|净之源净化
    How to do the clean plant construction / renovation quotation? | net source purification
    目前工业修建中的厂房缔造,因为越来越多的电子、医药和食品行业都对厂房提出了洁净等级请求,一起,公司扩张运营规划对原有洁净厂房的改扩建,也对工程报价人员提出一个新的研讨内容。
    At present the construction of the building industry to create, because more and more electronic, pharmaceutical and food industry are proposed on the plant clean level request, together with the expansion of the company expansion operation planning of the original clean workshop, also proposes a new research content of project bidding.
    这篇文章拟联系净之源5B/6A号修建扩建项目的施工过程中发现和存在的疑问,依据施工中所构成的实践工程本钱,剖析洁净厂房缔造和改建项目报价应留意的事项,从施工请求、办法费核算、报价战略和危险防备的视点对洁净厂房缔造及改造工程的招标提出本钱依据和报价建议。
    This article intends to contact the source of net construction process of No. 5B/6A building expansion project and found problems, based on the practice of project cost in construction, analysis and renovation project to create a clean workshop items should pay attention to the price, put forward cost basis and offer suggestions from the construction request, cost accounting, to quote strategy and the risk guard and create view reconstruction project on clean tender plants.
    目录:
    Catalog:
    节特别施工请求对工程造价的影响
    Section 1 the influence of special construction request on engineering cost
    1.1 依据项目详细状况对造价进行剖析
    1.1 analyze the cost according to the detailed status of the project
    1.2 GMP请求对土建工程报价的影响
    Effect of 1.2 GMP request on quoted price of Civil Engineering
    第二节怎么思考洁净区改造工程办法费
    How to consider the cost of the clean area reconstruction project in the second section
    手术室装修
    2.1 HSE费用
    2.1 HSE fee
    2.2拆改维护办法费
    2.2 dismantling maintenance measures fee
    第三节关于洁净室改造项目的报价战略
    The third section on the bidding strategy of the clean room reconstruction project
    3.1注重招标文件和答疑
    3.1 pay attention to bidding documents and answering questions
    3.2关于业主注重的要点进行报价歪斜
    3.2 on the owners pay attention to the main points of quotation skew
    3.3巧用不平衡报价
    3.3 skillfully using unbalanced quotation
    3.4报价的一致连贯性
    Consistent consistency of 3.4 quotation
    3.5重测算,轻定额
    3.5 calculation, light quota
    第四节危险躲避
    Fourth dangerous avoidance
    4.1查找招标文件的对立的当地
    4.1 find the opposite of the bidding document
    4.2 查看单项中隐含的辅佐作业
    4.2 check the implied auxiliary homework in the single item
    4.3以全体大局观审理图纸文件
    4.3 try the drawing document with the overall view
    4.4 关于进口货品的思考
    4.4 thoughts on imported goods
    4.5剖析业主的改变也许
    4.5 analyze the changes of owners